Coatings for Ferrous Sulphate Plant at Hartlepool Station

CSC Services have completed an upgrade to the Ferrous Sulphate Plant at Hartlepool Station for client EDF Energy installing a waterproof coatings system.

Failed epoxy coatings were removed from the bund walls, floors, walkways, staircases and handrails.

Deep cleaning of pipework, plant and equipment was undertaken using High Pressure Water Jetting and steam cleaning.

A Sikalastic 625 System incorporating glass reinforced fibre matting and an anti-slip finish was installed.

Mick Flounders, Contracts Director at CSC Services explains:

“The Sikalastic range of coatings are single component, cold applied liquid waterproofing membranes, that cure to form a seamless, durable and weather resistant waterproofing solution for exposed areas. “This coating was specified as it is cold applied, completely eliminating the risk of fire, and once installed achieves a high fire rating. Sikalastic is capable of curing in a range of conditions, making them ideal for use in unpredictable UK climate”.

With a 10-year guarantee from Sika Liquid Plastics, the waterproof coating system will outlast the life expectancy of the Ferrous Sulphate Plant at Hartlepool Station.

CSC Services are a trained and approved contractor for the Sika Liquid plastics range of products.  For more information about Sika Liquid Roofing Systems or any other waterproof coatings click here. 

Images showing the work in progress below:

Brickwork repointed, bund wall and floor coated. A new waterproof coating was also installed on tank lids.

Failed epoxy coatings removed from bund walls and floor, then a Sikalastic 625 System incorporating glass reinforced fibre matting and an anti-slip finish installed.

Failed epoxy coatings removed from staircases and handrails, and new Sikalastic 625 System installed

Bund walls recoated and steelwork re-coated to high standard

Steelwork around the bund access door was also re-coated and termination bars installed to provide a professional finish.